Sơn La power plant’s first turbine ready for full operation

Sunday, 12/26/2010 00:00
Acronyms View with font size
Thefirst turbine of Sơn La hydroelectric power plant is now ready for fulloperation after it was thorough checked by a State Council on December25.

The first turbine of the Sơn La hydroelectric power plant - Photo: VGP/Minh Huệ

The 400MW turbine began test run on December 17 this year, two years ahead of schedule.

The Sơn La Hydropower Plant is designed to have a total capacity of 2,400 MW with six turbines, each of 400 MW.

 

When construction finishes, the plant will provide over 10.2 billion kWh of electricity for the national power grid each year, contributing to the socio-economic development of the whole country and the northwestern region in particular./